First call to first swim.
Most new builds take 12–16 weeks once we break ground. Permitting adds another 4–8 weeks depending on your city and lot. You'll get a clear schedule at signing and weekly updates. One owner stays on your project the whole time.

- 01
Pre-build: Design & estimate
First call to see if we're a fit. Then we come walk the yard with you and listen. We bring back two or three design directions until one feels right. Itemized estimate, no surprises. We don't sign or take a deposit until you're ready.

- 02
Weeks 1–4: Permits & site layout
We pull the city permits. We run the structural engineering. We call for utility locates. If you're in an HOA, we hand you the engineered plans for your submittal. The city-side paperwork is on us. Once permits clear, we'll stake the pool footprint on your lot so you can walk it before we dig.

- 03
Week 5: Excavation
Demo first if anything has to come out. Then the dig. We haul away the spoils. The pool shape goes into the earth. This is the biggest-progress day of the whole build. You'll see your pool come out of the ground.

- 04
Weeks 6–7: Plumbing & steel
We rough in the hydraulic lines: skimmer, returns, main drain, and any spa or feature. We tie the structural rebar to the engineered spec. City inspectors sign off on plumbing and steel before anything gets buried.

- 05
Week 8: Shotcrete shell
One loud day. Pneumatic concrete shot at high pressure and hand-troweled into the shell. We start a 28-day water cure that afternoon. The shell needs to reach full strength before any finish goes on.

- 06
Weeks 9–11: Coping & tile
We set the coping (stone or concrete profile) on the bond beam. That defines the edge. Waterline tile goes in just below. These are the two details people notice every day, so we slow down to get them right.

- 07
Weeks 12–13: Decking
We pour and finish the concrete deck. Broom, salt, exposed aggregate, or stamped, your call. Expansion joints cut to the engineered plan. Mastic sealed at the coping line.

- 08
Weeks 14–15: Plaster & first swim
Interior finish goes on (pebble, quartz, or plaster) and water starts flowing the same day. We run startup chemistry every day through the 28-day cure. Final inspection, walkthrough on equipment and care, your first swim. After that, we're a phone call away. Same number, same owner, for the life of the warranty.

Step one is a walk-through.
Tell us about the yard. We’ll come walk it with you and figure out together whether your project is something we should take on.
Start my project